FS Register FRN 1029698

Five Star Rated on Google

13+ years specialist broking experience

General information, not advice. Written for general guidance and drawing on external sources as well as our own experience. It isn't a personal recommendation and doesn't take account of your circumstances — full disclaimer and sources.

The Essential Guide to Insurance for Complex Construction Risks 2026

Complex Construction Insurance UK: CAR, OCIP & Project Cover

January 06, 2026

The Underinsurance Problem Nobody Talks About

Most complex construction projects we review are underinsured — typically by 20 to 40%. Not because the people involved are careless, but because complex construction insurance is genuinely difficult to structure correctly. Sums insured drift below replacement value as material costs rise. DSU indemnity periods are set too short. Design liability sits in a gap between CAR and PI policies. Individual contractor policies overlap in some areas and leave voids in others.

This guide is designed to close those gaps. It covers every policy type relevant to complex construction in the UK, explains how they interact, and shows you exactly how to structure a programme that actually responds when something goes wrong — which, on complex projects, it eventually will.

20–40% Average underinsurance gap on complex construction programmes we review
£2.4m Financial exposure in our real claims example — covered by a properly structured programme
8–15% Average premium increase 2024–2026 on complex construction risks
0.3–0.8% Typical total insurance cost as a percentage of project value on a well-structured programme

1. Who Needs Complex Construction Insurance?

Complex construction insurance is not defined by a single threshold — it is defined by the combination of risk factors that standard commercial policies were not designed to handle. The following types of projects and parties routinely require specialist underwriting.

Developers and Project Owners

Developers carry ultimate financial exposure on any scheme. When a project is delayed, damaged, or triggers a liability claim, it is the developer who absorbs the uninsured loss. Owner-Controlled Insurance Programmes (OCIPs) are increasingly common on schemes above £10 million precisely because developers cannot afford to rely on every contractor and subcontractor carrying adequate, compatible cover. An OCIP gives the developer certainty of coverage across the entire supply chain under a single, unified policy — closing the gaps that individual contractor policies routinely leave open.

Main Contractors

Main contractors face risk from every direction simultaneously — their own works, their supply chain, their plant, their workforce, and their contractual obligations to the client. Most NEC3 and NEC4 contracts specify minimum insurance requirements, and failing to meet them is not merely a compliance issue; it can void the contract entirely and expose the contractor to uninsured claims from multiple parties at once. On design-and-build contracts, the interaction between the CAR policy and the professional indemnity policy demands particular attention.

Infrastructure and Civil Engineering Projects

Road schemes, rail works, tunnelling, bridge construction, and utility installation projects operate at a scale and duration where standard commercial policies simply were not designed to respond. These projects involve phased handovers, long exposure periods, complex ground conditions, and potential for third-party disruption that requires bespoke underwriting. Tunnelling in particular carries exposures — ground movement, third-party subsidence, utility damage — that many standard CAR policies exclude or heavily restrict.

Joint Ventures

When two or more contractors share responsibility for a project, the question of whose insurance responds — and in what order — must be resolved before work begins, not during a claim. A contractor's annual policy typically protects that contractor's interests; it does not automatically extend to protect a joint venture partner. A unified project-specific insurance programme with all JV parties named as co-insured removes this ambiguity entirely and is strongly preferable to relying on each party's own annual arrangements.

Renewable Energy Projects

Wind farms, solar installations, battery storage facilities, and grid-connected generation assets combine the risks of construction with the long-term operational exposures of an energy asset. Delays carry a particularly high financial cost because revenue generation does not begin until the project is complete — making Delay in Start-Up (DSU) insurance cover and parametric weather insurance far more critical here than on a standard residential or commercial build.

Demolition Contractors

Demolition contractors operate in some of the highest-risk conditions in the construction sector. Structural instability, hazardous materials (asbestos, contaminated ground), proximity to occupied buildings, and the potential for sudden third-party property damage all demand specialist cover with a properly informed underwriter. Non-disclosure of site conditions is one of the most common reasons demolition claims are contested — something specialist construction brokers encounter regularly.

What Insurance Does Your Project Need?

Select your project type below to see the recommended insurance programme for your specific risk profile.

Project Insurance Assessor

Select your project type to see the recommended cover for your risk profile

High-Rise Residential / Commercial Development

  • LEGAL Employers' Liability — minimum £5m, must be maintained throughout
  • ESSENTIAL Contractors All Risks (CAR) insurance — including temporary works, shoring, and scaffolding
  • ESSENTIAL Public Liability — minimum £10m on most city-centre schemes
  • ESSENTIAL Professional Indemnity — if design-and-build or any design responsibility
  • ESSENTIAL Delay in Start-Up (DSU) — critical if project has pre-lets, lender covenants, or revenue start dates
  • RECOMMENDED Latent Defects / Structural Warranty — increasingly required by lenders; 10–12 year cover post-completion
  • RECOMMENDED OCIP structure — if multiple contractors; eliminates inter-contractor coverage gaps
  • CONSIDER Cyber insurance — if BIM, connected site technology, or smart building systems in use
  • CONSIDER Environmental Liability — if contaminated land or proximity to watercourse

Infrastructure / Civil Engineering Project

  • LEGAL Employers' Liability — minimum £5m
  • ESSENTIAL Contractors All Risks (CAR) — bespoke wording; check tunnelling, ground movement, and utility strike exclusions
  • ESSENTIAL Public Liability — £10m–£50m depending on proximity to public and third-party infrastructure
  • ESSENTIAL Professional Indemnity — for design elements and engineering specifications
  • ESSENTIAL Environmental Liability — ground contamination, watercourse pollution, and ecology damage risks
  • RECOMMENDED Third Party Liability extensions — for disruption to roads, rail, utilities, and public access
  • RECOMMENDED Plant and Equipment — high plant values; check for hired-in plant under CPA terms
  • CONSIDER DSU — if project feeds into operational infrastructure with revenue or penalty consequences
  • CONSIDER Parametric weather cover — for exposed sites or seasonal weather-sensitive programme

Renewable Energy Project

  • LEGAL Employers' Liability — minimum £5m
  • ESSENTIAL Contractors All Risks (CAR) — including erection all risks for turbines, racking, inverters, and cabling
  • ESSENTIAL Delay in Start-Up (DSU) / Advanced Loss of Profits (ALOP) — critical; revenue does not start until grid connection and commissioning is complete
  • ESSENTIAL Professional Indemnity — for engineering design, grid connection design, and energy yield assessments
  • ESSENTIAL Public Liability — including for grid connection works and substation activities
  • RECOMMENDED Parametric weather insurance — automatic payout for weather events causing programme delay, without need to prove loss
  • RECOMMENDED Environmental Liability — for ground disturbance, ecology, and drainage risks
  • CONSIDER Marine transit cover — for offshore wind or remote site equipment shipment
  • CONSIDER Cyber insurance — for SCADA systems, grid monitoring, and smart inverter technology

Joint Venture / Multi-Party Project

  • LEGAL Employers' Liability — each employer must maintain their own compliant EL policy
  • ESSENTIAL Project-specific CAR policy — all JV parties named as co-insured; do not rely on individual annual policies
  • ESSENTIAL Unified Public Liability — single policy naming all JV members; prevents insurer cross-claiming between parties
  • ESSENTIAL JV Professional Indemnity — covers design liability across all contributing parties; individual PI policies may not extend to JV activities
  • RECOMMENDED OCIP structure — developer-controlled programme covering all contractors and subcontractors under one programme
  • RECOMMENDED DSU — if any JV party's delay or insolvency could impact project completion and revenue
  • CONSIDER Subcontractor default insurance — covers cost of replacing an insolvent or defaulting subcontractor
  • CONSIDER Legal expenses cover — for JV dispute resolution between parties

Demolition / Enabling Works

  • LEGAL Employers' Liability — minimum £5m
  • ESSENTIAL Public Liability — minimum £5m–£10m; must include vibration and weakening of support cover
  • ESSENTIAL CAR / Contract Works — for phased demolition with retained structures
  • ESSENTIAL Environmental Liability — asbestos, hazardous materials, and contaminated ground are standard demolition exposures
  • ESSENTIAL Full disclosure of site survey, asbestos reports, and structural assessments — non-disclosure is the leading cause of disputed demolition claims
  • RECOMMENDED Professional Indemnity — if providing pre-demolition surveys, structural assessments, or specification
  • RECOMMENDED Plant insurance — high plant values; track demolition equipment is expensive to replace
  • CONSIDER Adjacent property pre-condition surveys — documented evidence of pre-existing condition reduces disputes

Complex Refurbishment of Occupied Building

  • LEGAL Employers' Liability — minimum £5m
  • ESSENTIAL Public Liability — must extend to cover existing structure and occupiers; standard new-build wordings may be inadequate
  • ESSENTIAL CAR / Contract Works — specify cover for existing structure as well as works in progress
  • ESSENTIAL Professional Indemnity — particularly for structural alterations, M&E redesign, and listed buildings
  • RECOMMENDED Non-negligent liability / JCT 21.2.1 cover — protects against damage to adjacent property caused by lawful works, without negligence
  • RECOMMENDED Hot works extension — for cutting, welding, or any open-flame activities in occupied or partially occupied premises
  • CONSIDER Business interruption for the occupier — if works disruption causes measurable financial loss to the occupying business
  • CONSIDER Latent Defects — if significant structural works are being carried out

2. The Core Policies: What They Cover and Where the Gaps Are

Each policy in a complex construction programme covers a distinct risk. Understanding what each one does — and critically, what it does not — is the only way to ensure the programme has no voids.

Contractors All Risks (CAR)

CAR insurance is the foundation of any construction programme. It covers physical loss or damage to the works under construction — the contract works themselves, site materials, temporary works, and usually the contractor's own plant and equipment. What CAR does not cover is equally important to understand:

  • The cost of correcting a design error (that is PI territory)
  • Consequential financial loss from a delay (that is DSU territory)
  • Latent defects discovered after practical completion (that is latent defects insurance)
  • Deliberate acts, poor workmanship, or faulty design — these are commonly excluded from the physical damage cover itself
The CAR / PI boundary is where complex projects get caught out. If a structural element fails due to a design error, the CAR policy will not pay to correct the design — only to repair consequential physical damage to other parts of the works. If the PI policy limit is too low to cover the full reinstatement cost, there is an uninsured gap. On design-and-build contracts, ensure the PI sum insured is sufficient to fund full reinstatement, not just the design fee.

Professional Indemnity (PI)

Professional Indemnity insurance covers claims arising from professional errors, omissions, or negligence in design, specification, advice, or project management. On complex projects, PI must be carried by every party with design responsibility — architects, structural engineers, M&E consultants, and increasingly, design-and-build contractors who assume responsibility for the performance of the works they specify.

Key structuring points for PI on complex projects:

  • The retroactive date must go back to the start of the project, not just the current policy year
  • Run-off cover must be arranged after the project completes — PI is a claims-made policy, meaning the policy in force when the claim is made responds, not the one in force when the error occurred
  • Collateral warranties to funders, purchasers, and tenants extend your PI obligations beyond the original client relationship and must be factored into limit adequacy

Delay in Start-Up (DSU) / Advanced Loss of Profits (ALOP)

DSU insurance covers the financial losses caused when physical damage to the works delays the project's completion date and income start date. It is an extension of the CAR policy — it can only be triggered by physical damage that is itself covered under the CAR. Common mistakes in DSU structuring on complex projects include:

  • Setting the indemnity period based on the planned programme rather than the worst credible delay scenario
  • Underestimating the sum insured by excluding financing costs, penalty clauses, and increased operating expenses
  • Using a 90-day time excess when lender covenants or pre-let agreements require performance within 30 days of the planned date

Latent Defects Insurance (Structural Warranty)

Latent defects insurance — also called structural warranty or inherent defects insurance — covers the cost of repairing structural defects that were present at practical completion but not discovered until later. It provides cover for 10 to 12 years from completion and protects the building owner, any future purchaser, and the funder. It is increasingly required by lenders as a condition of development finance and by commercial tenants as a condition of long leases.

Unlike CAR insurance, latent defects cover does not depend on proving negligence — it responds to the defect itself, making claims faster and less contentious than pursuing a design team under their PI policy.

Environmental Liability

Construction on brownfield sites, near watercourses, or in areas with historic industrial use carries significant environmental liability exposure. Standard public liability policies typically exclude gradual pollution and environmental damage — meaning that a slow ground contamination event or damage to a protected habitat may not be covered. A standalone environmental liability policy covers:

  • Remediation costs for contaminated land and groundwater
  • Third-party claims for environmental damage
  • Regulatory investigation costs and clean-up orders
  • Damage to protected ecology — an increasingly significant exposure under the Environment Act 2021's biodiversity net gain requirements

Cyber Insurance for Construction

Modern construction projects are heavily digitised — BIM platforms, connected site sensors, project management software, drone data systems, and smart building controls all represent cyber exposure. A ransomware attack on a contractor's BIM environment during a complex project can result in data loss, programme disruption, and significant costs. Cyber insurance for construction should be considered on any project using connected technology, particularly where the contractor holds sensitive client data or project specifications.

3. Which Policy Responds to Which Risk?

One of the most common sources of coverage gaps on complex projects is uncertainty about which policy is supposed to respond to a given event. The matrix below maps the seven most significant risk categories against the core policies in a complex construction insurance programme.

Risk Event CAR Public Liability Employers' Liability Professional Indemnity DSU Latent Defects Environmental
Fire / flood damage to works in progress ● – – – ● – –
Third-party property damage during works ● ● – – – – –
Worker injury on site – – ● – – – –
Design error causing structural failure ● – – ● – – –
Project delayed due to insured physical damage ● – – – ● – –
Structural defect discovered post-completion – – – ● – ● –
Ground / water contamination event – ● – – – – ●
Cyber attack disrupting project systems – – – – – – –
● Primary response ● Responds if triggered by primary event ● May respond — check policy wording – Does not respond

Note: Cyber attacks on construction project systems are not covered by any of the above policies — a standalone cyber insurance policy is required.

4. OCIP and Project-Specific Insurance Structures

On complex, high-value, or multi-party projects, the question of how to structure the insurance programme — who buys it, who it covers, and how it interacts with individual contractor policies — is as important as the policy terms themselves.

Owner-Controlled Insurance Programmes (OCIP)

An OCIP is a consolidated insurance programme arranged and controlled by the project owner or developer, covering all contractors and subcontractors on the project under a single set of policies. The primary advantages are:

  • No coverage gaps between contractors — all parties are insured under the same wordings with the same insurer, eliminating disputes about whose policy responds
  • Higher aggregate limits — a single programme can carry higher limits than the sum of individual contractor policies, important on high-value projects
  • Consistent claims handling — one insurer, one adjuster, one process, regardless of which contractor was involved in an incident
  • Cost efficiency at scale — on large projects, the developer can often buy better terms than small contractors can access individually

OCIPs require careful management — contractors' own annual policies must be endorsed to exclude the project, and the OCIP must be clearly documented in subcontract agreements. Employers' liability remains an exception: each employer must maintain their own compliant EL policy regardless of any OCIP arrangement.

Project-Specific vs Annual Programme

For most complex projects, a project-specific CAR and DSU policy is preferable to extending an annual programme, because:

  • The sum insured is set to the contract value of the specific project, not an aggregate across multiple schemes
  • The policy period aligns exactly with the build programme plus a maintenance period
  • Bespoke extensions — tunnelling, demolition, vibration, ground movement — can be negotiated for the specific site conditions
  • A claim on a project-specific policy does not affect the contractor's annual programme or their renewal terms

5. The Underinsurance Gap: Why It Happens and How to Close It

Underinsurance on complex construction projects is systemic and largely avoidable. The most common causes we identify when reviewing programmes are:

Reinstatement Value Drift

Construction costs have risen substantially since 2021 — materials, labour, and specialist subcontractor rates have all increased significantly. A sum insured set at tender stage in 2022 based on a £12 million contract value may need to be £15–16 million to fund reinstatement at 2026 rates. The policy sum insured must be reviewed — not just at renewal, but at any point where material or labour costs have moved significantly.

Professional fees, debris removal, and compliance costs are routinely omitted. Reinstating a fire-damaged structure requires more than the cost of rebuilding. Architect's fees, structural engineer costs, planning resubmission, removal of debris, and compliance with updated building regulations all add to the reinstatement cost — and all need to be included in the sum insured. These items alone can add 15–25% to the cost of a major reinstatement.

DSU Sum Insured Shortfall

DSU underinsurance is particularly common. The sum insured must cover not just lost revenue but all financial consequences of the delay: financing costs on the development loan, contractual penalties for late completion, increased operating costs, and any loss of pre-sales or pre-let income. Calculating the DSU sum insured purely on projected net revenue consistently understates the exposure.

PI Limit Inadequacy on Design-and-Build Contracts

On design-and-build contracts, the contractor assumes PI exposure far exceeding the design fee alone. If a structural design error requires the demolition and reconstruction of a major element of the works, the PI claim may be measured in millions — not thousands. PI limits on complex D&B contracts should be set at a level commensurate with the worst credible design failure scenario, not as a round number or a percentage of fee income.

6. Claims on Complex Construction Projects: What to Do

Real Claim Example — Mixed-Use Development, Birmingham

A main contractor was appointed on an £18 million mixed-use development comprising retail units and residential apartments. Midway through the project, the key structural steelwork subcontractor entered insolvency without warning, causing an immediate halt to that phase of the works.

The consequences cascaded quickly: a four-month delay to programme, liquidated damages triggered under the main contract, a 12% increase in material costs for the replacement steelwork package, and loss of anticipated rental income for the developer during the extended void period. Total financial exposure: £2.4 million.

Because the project had a properly structured CAR policy and DSU cover with a 30-day time excess and 18-month indemnity period, the insurer was able to respond to the majority of the financial loss. The claim was complex — establishing the causal link between the subcontractor default, the physical delay event, and the DSU trigger required detailed programme analysis — but the documentation that had been maintained from project inception made that possible.

The lesson: DSU claims require evidence of exactly when the delay began, what caused it, and precisely what financial loss resulted from each day of overrun. Projects without contemporaneous records rarely recover their full entitlement.

The Five Rules of Claims Management on Complex Projects

  1. Notify immediately. Every commercial construction policy requires prompt notification of incidents. Late notification — even by a few weeks — can give an insurer grounds to reduce or decline a claim. When in doubt, notify first and establish the facts second.
  2. Preserve all documentation. Programme records, site diaries, photographs, RAMS, correspondence, subcontract agreements, and meeting notes are all potentially relevant to a complex construction claim. Establish a document preservation protocol at project inception, not after an incident occurs.
  3. Do not admit liability. In a multi-party construction environment, the cause of an incident is rarely immediately clear. Do not admit liability or make concessions to third parties without insurer consent — doing so can prejudice coverage.
  4. Engage your broker immediately. Your broker's role in a complex claim is to manage the insurer relationship, ensure the loss adjuster's appointment is appropriate for the scale of the project, and advocate on your behalf if coverage questions arise.
  5. Appoint experts early. On large claims, a specialist loss adjuster, a quantum expert, and potentially a legal adviser will all be required. The insurer will appoint their own loss adjuster — you should have independent representation to ensure your interests are properly presented. See our guide to construction insurance claims examples for more on how complex claims unfold.

7. Risk Management Practices That Reduce Premiums and Claims

Insurers price complex construction risk on the basis of the probability and severity of claims. The more evidence you can provide that your project is well-managed, the better the terms you will achieve — not just at inception, but at renewal and on future projects.

Risk Management Practice Insurance Benefit Where It Has Most Impact
Pre-start ground investigation and utility surveys Reduces exclusions on utility strikes and ground movement; may reduce PL excess Civil engineering, groundworks, demolition
BIM coordination and clash detection Demonstrates design risk control; supports PI limit adequacy arguments High-rise, complex M&E, design-and-build
Subcontractor pre-qualification and insurance vetting Reduces insurer concerns about supply chain risk; supports OCIP or project-specific structure All complex projects with multi-tier supply chains
Real-time site monitoring (IoT sensors, drones) Early warning of structural movement, water ingress, or fire — reduces severity of claims High-rise, tunnelling, occupied building refurbishment
Documented CDM compliance and principal contractor procedures Reduces EL and PL claims frequency; demonstrates regulatory compliance to underwriters All notifiable projects
Programme and contingency management documentation Essential evidence for DSU claims; demonstrates proactive delay management to insurers Any project with DSU cover in place
Pre-condition surveys of adjacent properties Provides baseline evidence that reduces third-party subsidence and damage disputes Urban sites, demolition, tunnelling

Frequently Asked Questions

Insurers typically define complex construction as projects involving high contract values (usually above £5 million), specialist engineering or design, multiple contractors or joint venture structures, unusual ground conditions, proximity to sensitive third-party property, long build programmes, or specialist activities such as tunnelling, demolition, or offshore works. Any one of these factors may push a project into specialist underwriting territory; combinations of them almost certainly will. The defining characteristic is that the risk profile cannot be adequately assessed — or responded to — by standard off-the-shelf commercial policies.

The core policies are Contractors All Risks (CAR) insurance, public liability, employers' liability, and professional indemnity. Depending on the project, additional covers may include Delay in Start-Up (DSU) insurance, latent defects insurance (structural warranty), environmental liability, cyber insurance, and parametric weather cover. Joint ventures and OCIP structures require specific policy arrangements to ensure all parties are covered under a unified programme. Use the Project Insurance Assessor in this guide to see the recommended programme for your specific project type.

An Owner-Controlled Insurance Programme (OCIP) is a consolidated insurance structure where the project owner or developer arranges a single insurance programme covering all contractors and subcontractors on a project, rather than requiring each party to provide their own policies. OCIPs are most appropriate on high-value projects — typically above £10 million — where the developer needs certainty of coverage across the supply chain and wants to eliminate the gaps, overlaps, and disputes that arise when multiple individual contractor policies interact. Each employer within the OCIP must still maintain their own employers' liability policy.

Latent defects insurance — also called structural warranty or inherent defects insurance — covers the cost of repairing structural defects that were present at practical completion but not discovered until later. It typically provides cover for 10 to 12 years from practical completion, protecting building owners, funders, and future purchasers. Unlike a PI claim, it does not require the claimant to prove negligence — it responds to the defect itself, making it faster and less contentious than pursuing the design team. It is increasingly required by lenders as a condition of development finance and by institutional landlords as a condition of accepting a long lease.

The most common causes of underinsurance on complex projects are: sums insured set at tender stage not keeping pace with rising material and labour costs; failure to include professional fees, debris removal, and building regulation compliance costs in the reinstatement sum; DSU indemnity periods set too short relative to the actual worst-case delay risk; PI limits on design-and-build contracts inadequate relative to the structural liability assumed; and gaps between individual contractor policies on multi-party projects where no unified structure is in place. Miller & Partner's review of complex construction programmes typically identifies underinsurance gaps of 20–40%.

No. Contractors All Risks (CAR) insurance covers physical loss or damage to the works — it does not cover the cost of correcting the design error itself. The cost of redesign and any resulting additional construction costs arising directly from the design fault fall under Professional Indemnity (PI) insurance, which must be carried by the party with design responsibility. Where CAR may partially respond is to consequential physical damage to other parts of the works caused by a structural failure triggered by the design error — but the design correction itself is always PI territory. Ensuring CAR and PI limits are coordinated and together sufficient to fund full reinstatement is one of the most important structuring decisions on a complex project.

Parametric insurance pays out automatically when a predefined trigger event occurs — such as wind speeds exceeding a set threshold, rainfall above a certain level, or temperature falling below a critical point — without the need to prove actual loss. It is particularly useful for construction projects in exposed locations or with tight completion schedules where adverse weather represents a significant programme risk. Renewable energy projects and offshore construction are the most common users in the sector. The key advantage of parametric cover is speed of payment — there is no claims investigation, no loss adjuster, and no need to quantify the loss; the trigger event itself determines the payout.

On a joint venture project, the parties must agree before work commences whether each JV member will rely on their own annual policies or whether a project-specific unified programme will be arranged. Relying on individual annual policies creates significant risks: different policy wordings, different insurers, different excesses, and potential disputes between insurers about which policy responds to a given claim. A project-specific JV programme with all parties named as co-insured provides much greater certainty. It eliminates the risk of an insurer seeking contribution from a co-insured's policy and ensures a single, consistent response to any incident on the project.

Complex construction insurance is individually rated based on contract value, project type, programme duration, ground conditions, site location, the contractor's claims history, and the extent of design responsibility. As a general guide, CAR premiums on complex projects typically range from 0.1% to 0.4% of contract value, with DSU, PI, and other covers priced separately. The total insurance cost on a well-structured programme — including all core and specialist covers — is usually in the range of 0.3–0.8% of total project value. Premiums have risen 8–15% since 2024 driven by increased claims activity, inflation in reinstatement costs, and harder market conditions in specialist construction lines.

John Miller — Director, Miller & Partner
Written and reviewed by John Miller Director & Principal Broker, Miller & Partner Over 13 years of specialist commercial insurance experience. Former #1 Account Executive at Brown & Brown and #1 Salesperson at AXA. Miller & Partner Limited is an Appointed Representative of Gauntlet Risk Management Ltd, which is authorised and regulated by the Financial Conduct Authority. Direct access to Lloyd's Market and specialist MGA schemes.

Related Guides from Miller & Partner

Complex Construction InsuranceConstruction InsuranceCommercial Construction Insurance
Back to Blog
About this article General information, not advice. Published for general guidance and drawing on external sources as well as our own experience. It is not a personal recommendation, a quotation, or an offer of cover, and it doesn't take account of your circumstances. Read more + Close −

Where the information comes from

Our articles are compiled from a range of sources: regulators and public bodies such as the FCA, the Civil Aviation Authority, the Health and Safety Executive and Companies House; government publications and legislation; industry and trade bodies; insurer and market documentation; and published research and news reporting. Not everything stated originates from Miller & Partner. Where information comes from a third party we believe it to be accurate at the date of publication, but we haven't independently verified every external source and we don't warrant its accuracy or completeness. Where a point matters to a decision you're making, go to the original source and check it.

Figures, examples and case studies

Premium ranges, cost figures, limits and worked examples are illustrative only. They are not quotations, not offers of cover, and no cover is provided or implied on the basis of them. What you're actually charged depends on underwriting, and what you're actually covered for depends on the policy wording issued to you. Where an article includes a claim example, scenario or case study, it is illustrative unless we say otherwise — such examples are typically composites written to show how a policy section responds, and they don't describe an identifiable client, claim or settlement.

Interactive tools

Any calculators, cover checkers, risk assessors or similar tools on our site produce general guidance from the small number of answers you give them. They can't see your business, and their output is not a personal recommendation, an assessment of your actual risk, or a quotation.

Rules and market conditions change

Law, regulation, tax treatment, insurer appetite and policy wordings all change, sometimes at short notice. Content is accurate to the best of our knowledge on the date shown on the article and we don't undertake to update it as things move. An article you're reading some time after publication may be out of date.

Third parties and external links

References to insurers, underwriters, trade bodies, software, training providers or other organisations are for information only. They don't imply endorsement, recommendation, partnership or affiliation in either direction unless stated. We're not responsible for the content of external websites we link to.

Not legal, tax or accounting advice

Nothing here is legal, tax, accounting or regulatory advice. Where an article discusses statutory duties, contract terms or compliance obligations, take advice from an appropriately qualified professional on your own position before acting.

How we write these

We use AI tools in researching and drafting our published content. Every article is reviewed and signed off by a named, accountable person at Miller & Partner before it is published, and responsibility for what appears here rests with us.

Our regulatory status

Miller & Partner Ltd is an Appointed Representative of Gauntlet Risk Management Ltd, which is authorised and regulated by the Financial Conduct Authority (FRN 308081). Miller & Partner Ltd is entered on the FCA Register under reference 1029698. Registered in England and Wales, company number 16206282. Registered office: Vivian House, Roman Bridge Close, Mumbles, Swansea, SA3 5BG.

Spotted something wrong?

We'd rather know. Email [email protected] or call 01792 001350 and we'll review and correct it.

For advice on your own insurance arrangements, speak to us directly — that's when we can take your circumstances into account and give you a recommendation.

Ready to protect your business?
Get expert advice and a tailored commercial insurance quote today.

✔ Independent broker
✔ Access to leading UK insurers
✔ Fast turnaround

[Request a quote]

[[email protected]]
[Call 01792 001350]

Exclusive Offer

Free Insurance Review
& Zero Broker Fee

Let us review your current insurance and see if we can improve your cover while reducing the cost.

✓
Free no-obligation insurance review tailored to your business
£
Zero broker fee on all new policies
⚡
Fast response from a real insurance specialist

You're in 🎉

Thanks for requesting your free review. We'll be in touch shortly.

🔒 No spam, ever. Your details are safe with us.

We're an Appointed Representative of Gauntlet Risk Management Ltd, which is authorised and regulated by the FCA. You can check our entry on the FCA Register.

MEET THE Director

Hey, I'm John!

I started Miller & Partner with the aim to bring back personable, approachable broking to UK businesses who were tired of large corporate brokers and feeling like they were just another number.

I have built this brokerage up with no pushy sales techniques or big business tactics, just honest, approachable and professional relationships with my clients.

Over 13 years experience in business insurance

Client first approach

5* rated broker on Google

Office: Vivian House, Roman Bridge Close, Mumbles, Swansea, SA3 5BG

Miller & Partner Ltd is an Appointed Representative of Gauntlet Risk Management Ltd, which is authorised and regulated by the Financial Conduct Authority (FRN 308081). Miller & Partner Ltd is entered on the Financial Services Register under firm reference number 1029698. You may check this on the Financial Services Register by visiting the FCA website at https://www.fca.org.uk/firms/financial-services-register or by contacting the FCA on 0800 111 6768. Miller & Partner Ltd is registered in England & Wales, company number 16206282. Registered office: 20 Vivian House, Roman Bridge Close, Swansea, SA3 5BG.